Project: "Krumovo - Parvomai, km 164+575.00 - km 202+300.00" from the first railway line on the object "Electrification and reconstruction of the railway line Plovdiv - Svilengrad, corridors IV and IX" Design phase: Definitive design Employer: TERNA Contractor company (Consultant): Vector-Bul Ltd. - subcontractor Excerpt from the reference: Vector-Bul company
“Electrification and reconstruction of the Plovdiv – Svilengrad railway line, corridors IV and IX” Parvomai – Svilengrad, km 202+300.00 – km 298+800.00 phase 2 in the section 202+300 to 231+560 from the first railway line
Project: "Electrification and reconstruction of the Plovdiv - Svilengrad railway line, corridors IV and IX" Parvomai - Svilengrad, km 202+300.00 - km 298+800.00 phase 2 in the section 202+300 to 231+560 from the first railway line Design phase: Definitive design Employer: ASTALDI Contractor company (Consultant): Vector-Bul Ltd. - subcontractor Excerpt